Topic:  IPF Update Letter

Topic:  IPF Update Letter
Author
Message
72 Bobcat
General User

Member Since: 2/28/2007
Location: Harleysville, PA
Post Count: 46

Status: Offline

  Message Not Read  IPF Update Letter
   Posted: 5/26/2013 9:44:38 AM 

In yesterday's mail I received a letter from Jim Schaus (dated May 25, 2013) updating the status of the IPF. The letter states the Design-Build project will be done by Turner Construction of Columbus with construction beginning next week.  It goes further to say the facility is scheduled to be erected during July, August and early September with hopes of having access for football by early December.  More of a complete occupancy will be available for all users at the end of January 2014.  Final completion to include landscaping and paving will conclude byJune 2014.

Day to day operations will be managed by the "Office of Studend Affairs".  The next sentence says, "Our two units share a number of synergies and maintain great working relationships."  I guess our two units is Office of Student Affairs and Athletics??  Don't know if there was such a thing as Office of Student Affairs in 1972.

Just wanted to share what I received.  I am excited for the upcoming footballl season and by the early success of football recruiting.  I can't remember any other time where we had perennial high expectations for our team.

 

Back to Top
  
catfan28
General User

Member Since: 6/11/2011
Location: Athens, OH
Post Count: 1,503

Status: Offline

  Message Not Read  RE: IPF Update Letter
   Posted: 5/26/2013 10:07:48 AM 
I drove by yesterday and can't believe they STILL haven't started on any construction. Not even clearing a tree. Hope it's correct that the project starts next week, but goodness...this thing sure has been delayed.
Back to Top
  
KyleWvr13
General User



Member Since: 11/9/2010
Location: Pottstown, PA
Post Count: 501

Status: Offline

  Message Not Read  RE: IPF Update Letter
   Posted: 5/26/2013 12:13:41 PM 
catfan28 wrote:
I drove by yesterday and can't believe they STILL haven't started on any construction. Not even clearing a tree. Hope it's correct that the project starts next week, but goodness...this thing sure has been delayed.


Maybe they had to wait until the new turf in Peden was installed?  I don't know but it's my only guess.  I'm just ready to see SOME kind of progression on it.
Back to Top
  
TWT
General User



Member Since: 12/20/2004
Location: Alexandria, VA
Post Count: 5,171

Status: Offline

  Message Not Read  RE: IPF Update Letter
   Posted: 5/26/2013 7:30:00 PM 
A bear bones facility like this can be put up pretty quick. Glad to see that it will be largely up by the first home game when recruits are coming into town an available for use in December in advance of the bowl game.


Most Memorable Bobcat Events Attended
2010 97-83 win over Georgetown in NCAA 1st round
2012 45-13 victory over ULM in the Independence Bowl
2015 34-3 drubbing of Miami @ Peden front of 25,086

Back to Top
  
turfcat
General User

Member Since: 1/19/2011
Post Count: 70

Status: Offline

  Message Not Read  RE: IPF Update Letter
   Posted: 5/31/2013 9:03:35 AM 
Trees were removed yesterday, fences are coming down and project is picking up steam as we speak. Peden field replacement is finishing up this weekend also.
Back to Top
  
Alan Swank
General User

Member Since: 12/11/2004
Location: Athens, OH
Post Count: 7,213

Status: Offline

  Message Not Read  RE: IPF Update Letter
   Posted: 5/31/2013 9:42:41 AM 
Uncle Wes wrote:
A bear bones facility like this can be put up pretty quick. Glad to see that it will be largely up by the first home game when recruits are coming into town an available for use in December in advance of the bowl game.


Guys, the building plans haven't even been approved yet according to a source who would know.
Back to Top
  
Robert Fox
General User

Member Since: 11/16/2004
Location: Knoxville, TN
Post Count: 2,039

Status: Offline

  Message Not Read  RE: IPF Update Letter
   Posted: 5/31/2013 11:17:32 AM 
Alan Swank wrote:
Uncle Wes wrote:
A bear bones facility like this can be put up pretty quick. Glad to see that it will be largely up by the first home game when recruits are coming into town an available for use in December in advance of the bowl game.


Guys, the building plans haven't even been approved yet according to a source who would know.


If that's true, I'm surprised the General Contractor has been named. I would assume multiple contractors bid on something, presumably a workable set of plans. Not good news.
Back to Top
  
turfcat
General User

Member Since: 1/19/2011
Post Count: 70

Status: Offline

  Message Not Read  RE: IPF Update Letter
   Posted: 5/31/2013 12:46:46 PM 
I was told today by a reliable source that site soil removal will start by mid next week. The trees are down and chipped except for the logs and will be hauled away soon.
Back to Top
  
colobobcat66
General User

Member Since: 9/1/2006
Location: Watching the bobcats run outside my window., CO
Post Count: 4,547

Status: Offline

  Message Not Read  RE: IPF Update Letter
   Posted: 5/31/2013 2:56:49 PM 
Alan Swank wrote:
Uncle Wes wrote:
A bear bones facility like this can be put up pretty quick. Glad to see that it will be largely up by the first home game when recruits are coming into town an available for use in December in advance of the bowl game.


Guys, the building plans haven't even been approved yet according to a source who would know.
. Not approved by who- some government agency or who? Not enough info to mean much
Back to Top
  
Valley Cat
General User



Member Since: 12/28/2004
Location: Jackson Twp., OH
Post Count: 1,214

Status: Offline

  Message Not Read  RE: IPF Update Letter
   Posted: 6/1/2013 8:31:57 AM 
If they put up videos like this. Don't they have to get a move on?

http://www.youtube.com/watch?feature=endscreen&NR=1&v=G9xadFhue3I
Back to Top
  
Alan Swank
General User

Member Since: 12/11/2004
Location: Athens, OH
Post Count: 7,213

Status: Offline

  Message Not Read  RE: IPF Update Letter
   Posted: 6/1/2013 11:19:19 AM 
colobobcat66 wrote:
Alan Swank wrote:
Uncle Wes wrote:
A bear bones facility like this can be put up pretty quick. Glad to see that it will be largely up by the first home game when recruits are coming into town an available for use in December in advance of the bowl game.


Guys, the building plans haven't even been approved yet according to a source who would know.
. Not approved by who- some government agency or who? Not enough info to mean much


This is a design build project.  As it was explained to us, the final plans have not been approved yet but should be by July 1.  Approval does include state agencies.

http://www.dbia.org/about/designbuild/

Last Edited: 6/1/2013 11:19:39 AM by Alan Swank

Back to Top
  
colobobcat66
General User

Member Since: 9/1/2006
Location: Watching the bobcats run outside my window., CO
Post Count: 4,547

Status: Offline

  Message Not Read  RE: IPF Update Letter
   Posted: 6/1/2013 12:15:32 PM 
Alan Swank wrote:
colobobcat66 wrote:
Alan Swank wrote:
[QUOTE=Uncle Wes]A bear bones facility like this can be put up pretty quick. Glad to see that it will be largely up by the first home game when recruits are coming into town an available for use in December in advance of the bowl game.


Guys, the building plans haven't even been approved yet according to a source who would know.
. Not approved by who- some government agency or who? Not enough info to mean much


This is a design build project. As it was explained to us, the final plans have not been approved yet but should be by July 1. Approval does include state agencies.

http://www.dbia.org/about/designbuild/[/QUOTE] thanks for the clarification
Back to Top
  
turfcat
General User

Member Since: 1/19/2011
Post Count: 70

Status: Offline

  Message Not Read  RE: IPF Update Letter
   Posted: 6/7/2013 1:10:26 PM 
Considering the final approval hasn't been granted yet it hasn't stopped progress from being made. Site is mostly cleared and and soil has been stripped and stockpiled. The second grass field closest to the golf course has been re-plumbed so it can continue to be maintained as is since it will remain in tact. Property looks totally different now with the trees gone and most of the fences down. One thing that stands out now is the need for power washing and some painting on the outside of the east seating area. The look of the old dingy masonry will detract from the aesthetics of the new facility.   
Back to Top
  
Showing Replies:  1 - 13  of 13 Posts